Guide for social landlords · 22 October 2026
Awaab's Law timescales: what social landlords must do, and by when
From 30 November 2026, Awaab's Law in England covers far more than damp and mould. The clocks stay the same; the list of hazards on them gets much longer, just as winter reports of cold homes start to rise.
What applies, and from when
| From | What is covered |
|---|---|
| 27 October 2025 | Phase 1: every emergency hazard, plus significant damp and mould hazards. |
| 30 November 2026 | Phase 2 adds significant hazards from excess cold, excess heat, falls (on the level, on stairs and between levels), structural collapse, fire and explosions, electrical hazards, and domestic hygiene (including personal hygiene and food safety). |
| No date set | Phase 3: the remaining hazards in the Housing Health and Safety Rating System, except overcrowding. |
The clocks
Phase 2 uses the same timescales as phase 1. A working day excludes weekends, Christmas Day, Good Friday and bank holidays in England and Wales. The 24-hour clock for emergencies runs through nights and weekends.
| Duty | Emergency hazard | Significant hazard |
|---|---|---|
| Investigate | Within 24 hours of becoming aware | Within 10 working days of becoming aware |
| Make safe (safety work) | Within the same 24 hours | Within 5 working days of the investigation ending |
| Written summary to the tenant | Within 3 working days of the investigation ending | |
| Supplementary preventative work | Start within 5 working days; if that is not reasonably practicable, as soon as it is and within 12 weeks | |
| Alternative accommodation | Offered if the home cannot be made safe in time | |
Simplified from the regulations. A tenant can also ask for a physical inspection, which sets its own 10 working day clock. Check the regulations for the detail.
When the clock starts
The duties begin when the landlord becomes aware of a potential hazard. The phase 2 guidance says that can happen in many ways: a tenant reporting it, someone reporting on their behalf (a representative, a friend, a neighbour), a routine inspection, a third party or a regulator. Whether a contractor's knowledge counts as yours depends on the contract, and the guidance suggests taking legal advice on it.
The guidance sets no special rule for reports made in the evening or online. The safe assumption is that a report your channels accept may start the clock, so a damp report made through a web form on a Friday night needs to be seen and sorted by severity, not left in a queue until Monday.
What to capture at the first contact
The quicker a report reaches the right severity, the more of the clock is left for the work. Most of what triage needs can be asked at the first contact:
- Where the problem is, how big it is, and how long it has been there
- Who lives in the home, and any vulnerabilities: age, health conditions, disability. The guidance says a tenant does not need medical evidence, and reports should generally be taken at face value
- Photos, where the tenant can take them
- When the home can be accessed, and how the tenant prefers to be contacted
- For phase 2 hazards, the specifics that decide severity: no heating or hot water, exposed wiring, a loose stair rail
What to keep on record
The regulations require the written summary and some documents, but the guidance goes further and recommends keeping:
- A record of the actions taken under Awaab's Law
- Every attempt to get access, as evidence of reasonable endeavours
- When the written summary was given to the tenant
- The condition of the hazard before work starts, with photos where needed
Records like these are what a board, the Regulator of Social Housing or the Housing Ombudsman will ask to see when a case is questioned.
Scotland and Wales
Scotland brought in its own damp and mould duties for social landlords on 6 October 2026. In Wales, responding to hazards has been part of the Welsh Housing Quality Standard since 1 April 2026. The detail differs from England, so check the guidance for your nation.
Where an assistant helps
Syntalyze puts a guided journey on your website that asks a tenant the triage questions above, sorts the report by hazard and severity, and opens the case with the clock already running. The deadlines for every open case sit on one dashboard, staff take over with a summary of what the tenant said, and every contact is recorded. It works in front of your contact centre and alongside your housing management system, at any hour.
See it for housing associations
This guide is general information, not legal advice. It reflects the regulations and guidance as published on 22 October 2026.
Sources
- The Hazards in Social Housing (Prescribed Requirements) (England) Regulations 2025 (SI 2025/1042)
- Awaab's Law in the social rented sector (GOV.UK collection)
- Awaab's Law Phase 2: guidance for social landlords
- Awaab's Law Phase 2: hazards guidance for social landlords
- Awaab's Law: guidance for landlords in Scotland
- Welsh Housing Quality Standard: responding to hazards (addendum)